Friday, October 29, 2010

Pavers going in



Pavers are being installed along the south side of the building, and in the pedestrian plaza outside of the front door.

Sidewalks to be poured



Forms and gravel base are in place for the Commerce Street and East Street sidewalks on the site.

Thursday, October 28, 2010

Carpet in theater



Carpet has been installed in the Visitor Center's theater, and acoustical ceiling tile installation is underway.  The large opening in the front wall will have an array of four LCD monitors to show the new multi-screen visitor orientation film.

Wednesday, October 20, 2010

Reclaimed wood flooring




The Tourism Council of Frederick County offices will be in one wing of the Frederick Visitor Center building, and feature a reclaimed industrial maple strip floor that has just been installed.



Sunday, October 10, 2010

Circuits, circuits!




Installation of light fixtures is underway as the electric room components are wired to respective areas of the building.


Thursday, October 7, 2010

Staining & polishing concrete floor





After several days of prepration, acid staining & polishing of the concrete floor for the exhibit area and hallway is now underway.