Lighting fixtures installed




The final steps of electrical work are underway, including installation of track lights for the future exhibits, and the uplights that reflect light off of the exposed tongue & groove wood ceiling.

Wednesday, November 17, 2010

Office floors finished




As Rockwell Construction heads into the home stetch on the building rehabiltation, the reclaimed industrial maple flooring in the Tourism Council office area of the new Frederick Visitor Center received the final coats of finish this week.  Baseboard will be installed next.


Tuesday, November 9, 2010

Vestibule roof




The flat roof over the entrance vestibule has been installed.

Monday, November 8, 2010

Reclaimed wood floor ready for sanding





The reclaimed industrial maple tongue & groove flooring has all been laid and is ready for a light sanding and refinishing.  This is the Tourism Council of Frederick County office area of the building.


Friday, November 5, 2010

Sidewalks poured




Concrete sidewalks have been poured along East Street, Commerce Street, and the service alley to the west of the building.  A ribbon of brick pavers will separate the East Street and Commerce Street sidewalks from the curb.  The main entrance to the building is reached via a pedestrian plaza of non permeable pavers.

Wednesday, November 3, 2010

Theater seats installed




The fixed theater seats have been installed in the new Frederick Visitor Center.  Two rows of additional movable seats can be set up on the flat floor area in front of the theater.  The four rows of fixed seats are on a sloped floor.  The normal use of the space will be to continuously show the new 4-screen visitor orientation film, "A Turn of the Wheel," however the room was designed to accommodate occasional meetings up front.